Industry
(a) |
Thermal
(b) |
River Valley/ Hydro Electric
(c) |
Mining (Coal)
(d) |
Mining (Non-Coal)
(e) |
Building, Construction Projects and Townships, Area Development projects
(f) |
Infrastructure*
(g) |
Any other projects
(h) |
Total | ||||
(A) Reason for pendency | ||||||||||||
i) Cases kept under Abeyance due to non- submission of Scrutiny Fees |
02 |
01 |
|
|
37 |
01 |
|
00 |
41 |
|||
ii) Cases yet to be referred to SEAC |
00 |
00 |
|
|
26 |
00 |
|
00 |
26 |
|||
iii) Cases under consideration with SEAC |
08 |
00 |
|
|
141 |
03 |
|
04 |
156 |
|||
iv) Additional information sought from Project Proponent (After SEAC) |
00 |
00 |
|
|
00 |
01 |
|
01 |
02 |
|||
v) Under Processing after SEAC’s recommendations |
03 |
00 |
|
|
00 |
00 |
|
00 |
03 | |||
vi) EC pending due to action due to violation case |
– |
– |
|
|
01 |
00 |
|
00 |
01 |
|||
Total ( ii to vi ) |
11 |
00 |
– |
– |
168 |
04 |
|
05 |
188 |
|||
(B) Period of pendency : (from the date of receipt in the SEAC) | ||||||||||||
(i) Pending since last 3 months |
4 |
00 |
|
|
91 |
00 |
|
2 |
97 |
|||
(ii) Pending since last 6 months |
4 |
00 |
|
|
50 |
03 |
|
2 |
59 |
|||
(iii) Pending since last 1 year |
– |
– |
|
|
– |
– |
|
– |
– |
|||
(iv) Pending since last 2 year |
– |
– |
|
|
– |
– |
|
– |
– |
|||
Total |
08 |
00 |
– |
– |
141 |
03 |
– |
04 |
156 |